Understanding California’s six-month deadline for filing claims against government entities can help injured victims protect their legal rights and avoid missing critical opportunities for compensation

By Ann Mazotta, California Business Journal

Share on:

A pothole, a broken curb, or a missing guardrail can injure someone on a road that belongs to a government agency. When that happens, California law sets a much shorter deadline than most people expect, and the claim must go to the right office. Missing either step can end the case before a court hears it. Here is how the Los Angeles process works.

Which Agency Owns the Road

Section 830 treats property as public when a government entity owns or controls it. According to the Los Angeles injury attorneys from Kermani LLP, people hurt by a road hazard often lose early weeks working out which agency is responsible. In Los Angeles, the answer can be the city, the county, or the state.

When a Road Defect Becomes Government Liability

Under Section 835, a public entity can be liable when the property was in a dangerous condition, the condition caused the injury, and it created a foreseeable risk of that kind of injury. The plaintiff must also show that an employee’s act created the condition or that the entity had notice of it in time to protect people. A dangerous condition is one that creates a substantial risk of injury, and under Section 830.2, a court can rule that a minor or trivial defect does not qualify.

Section 835.2 says constructive notice requires proof that the condition existed long enough, and was obvious enough, that the entity should have found it. StreetsLA takes pothole reports through MyLA311, so a saved confirmation can help show when the City was told.

The Six-Month Clock and What a Claim Must Say

Section 911.2 requires a claim for injury to a person to be presented within six months after the cause of action accrues, while claims for other losses get one year. A claim to the State’s Government Claims Program counts as presented on the date it is submitted with the $25 filing fee, with special rules for fee waivers. Section 910 lists what every claim must show.

  • Claimant details - name, mailing address, and where notices should go

  • The occurrence - date, place, and circumstances

  • The injury - a general description as known

  • Employees - names of public employees involved, if known

  • The amount - stated if under $10,000, otherwise only whether it is a limited civil case

What Happens After You File

Under Section 912.4, the entity must act on a claim within 45 days unless both sides agree in writing to more time. If it does not act, the claim is deemed rejected on the last day of that period. The City of Los Angeles issues a claim number after filing, and then its City Attorney’s office investigates.

Medical records, bills, and an injury diary matter here as they do in any injury case, as a general guide to documents a personal injury case needs explains. Gathering them early leaves less to scramble for later.

Court Deadlines and Late-Claim Relief

A lawyer watches a second clock that starts after the claim is filed. Under Section 945.6, suit is due within six months after written notice of rejection is delivered or mailed, or within two years from accrual if no such notice was given. If the six-month claim deadline was missed, Section 911.4 allows an application to present a late claim within a reasonable time, not more than one year after the injury, with the reason for the delay.

Section 911.6 requires the entity to grant that application in listed situations, including certain cases of a minor or an incapacitated claimant and excusable neglect that did not prejudice its defense. If it denies the application, Section 946.6 allows a petition to the court within six months after the denial.

Put the Deadline on Your Calendar

Write down the injury date and count six months from it, since that date controls the first deadline. Identify who owns the road, then file with that agency’s own office. Keep photos, reports, and any 311 confirmation together.

Copyright © 2026 California Business Journal. All Rights Reserved.

For California Business Journal Disclaimers, go to https://calbizjournal.com/terms-conditions/.

Advertisement

Advertisement: Ruth's Chris Steak House